WATER POLLUTION CONTROL FACILITY SLUDGE DRYING FACILITY, STAMFORD, CT

Owner: City of Stamford
Engineer: CH2MHill
Contract Amount: $6,845,291
Completion Date: October 2007

Pre-Construction Phase:

  • Review and comment on Engineer design development documents at discrete review points in the context of constructability and impact on price and/or schedule
  • Review Engineer furnished equipment submittals and manufacturing/shipping information in the context of constructability and impact on price and/or schedule

Construction Phase:

  • Interior and exterior selective demolition and debris removal to accommodate Drying Facility renovations
  • Extension of existing utilities to serve Drying Facility including potable water, fire protection, plant service water, process/sanitary wastewater, roof drain, natural gas and electric power
  • Architectural and structural renovations to Incinerator Building to accommodate installation and operation of Andritz Drum Drying System
  • Installation of Regenerative Thermal Oxidizer (RTO) units and Product Storage Silos
  • Installation of HVAC system, plumbing, electrical and fire protection systems within the Drying Facility
  • Storm water management during construction