NEW WASTEWATER TREATMENT PLANT & CENTRAL VACUUM PUMP STATION , PROVINCETOWN, MA

Owner: Town of Provincetown, MA
Engineer: Metcalf & Eddy Inc.
Contract Amount: WWTP: $3,995,176; Central Vacuum Pump Station: $589,244
Completion Date: October 2003

Wastewater Treatment Plant

  • Mobilization and demobilization
  • Concrete formwork, reinforcing steel
  • Outside yard piping
  • Receiving, storage, handling and installation of all mechanical, electrical and process equipment
  • All architectural related work associated with treatment plant
  • All electrical work associated with treatment plant
  • Testing and commissioning of facilities and equipment
  • Supply, installation, and testing of WWTP odor control system, sludge thickener and polymer system and plant water system

Central Vacuum Pump Station

  • Underground piping and trench work
  • Foundation and concrete work including concrete slabs, equipment bases and transformer pad
  • WWTP building work
  • Design and provide temporary earth supports for vacuum pump station building excavation
  • Miscellaneous steel, metal, HVAC and plumbing work
  • Flushout
  • Instrumentation installation and wiring
  • Pressure gauges
  • Piping tie-ins to existing tankage and piping
  • Field welds and fittings
  • Above ground piping work
  • Engineering and design of piping